NCDOT Swain County Storage Building
Location: | Bryson City, NC |
Contract Amount: | $785,000 |
Completion Date: | January 2023 |
Project is a new one-story pre-engineered metal building, approximately 3,153 SF. The construction included administration offices, conference area, break room, employee lockers, and bathrooms, covered equipment storage and entrance, tool walls and storage, small parts storage, large parts and equipment storage, and clear span maintenance bay areas with coiling doors. Scope of Work included site clearing, grading, storm water pipe installation and drainage, domestic water and sewer installations, 6” Concrete slab over vapor barrier, 4” stone base w/ 3” Rigid Perimeter Insulation, Standing seam metal roof on Purlins with fiberglass batt insulation suspended from metal building manufacturer’s standard fabric liner, PEMB Concealed fattener metal panel system, asphalt driveway and parking, plumbing, HVAC and electrical.